What Does It Cost to Build a Fourplex in BC? By Region

The Province's own cost estimate for its standard small-scale housing designs puts a Vancouver fourplex at about $2.25 million in hard construction costs, and Prince George at roughly three quarters of that per square foot. Here are the published numbers, region by region, and what they leave out.

The short answer

  • The Province's 2024 Class D estimate puts the hard construction cost of its standard 4-unit designs in Vancouver at $2,245,893 to $2,307,250, or $425 to $446 per built square foot.
  • Its regional review ranges from $275 per sq ft (Chilliwack, Kamloops, Nanaimo and Victoria, Prince George) to $475 per sq ft (Vancouver).
  • Hard cost is not the budget. Soft costs, contingency, development cost charges, utility connections, demolition and land all come on top.
  • Construction prices are still rising: Statistics Canada's residential index for Q1 2026 was up 1.4% year over year in Vancouver and 6.0% in Victoria.

The short answer

  • $425 to $446 hard cost per sq ft, the Province's 4-unit designs (Vancouver base, 2024)
  • $275 to $475 per sq ft range across seven BC regions in the same review
  • +26% soft costs on top of hard costs, Lower Mainland and Fraser Valley (Province, 2023)

There is one public, BC-specific source that prices small multiplexes design by design: the Class D cost estimate prepared in August 2024 for the BC Ministry of Housing's Standardized Designs Catalogue. It priced ten designs (fourplexes, a 4-unit townhouse, a triplex, duplexes and backyard suites) using Vancouver as the base case, then compared square-foot costs in other regions.

For a 3-storey fourplex of about 5,300 sq ft, it estimates $2,245,893 to $2,293,518 in hard construction cost, about $561,473 to $573,380 per unit. That is the cost of building the structure itself. It does not include design fees, permits, utility connections, demolition of an existing house, or the land.

Cost by design: fourplex, triplex, duplex, garden suite

These are the Province's estimates for each standard design, all priced at Vancouver rates. Built square footage is the total floor area across all storeys.

Why several designs of the same type: the Province's standardized design catalogue offers more than one plan per building type so it fits different lots and households. Quadplex 01 has 8 bedrooms across the four units; Quadplex 02 has 12 on a wider footprint. Duplex 01 is two storeys and 2,056 sq ft, Duplex 02 is three storeys and 3,084 sq ft, and Duplex 03 sits between them. The ADUs run from a 750 sq ft one-storey, one-bedroom suite (ADU 02) to a 1,715 sq ft two-storey, three-bedroom unit (ADU 03). Bigger and taller plans cost more in total, but the cost per square foot usually drops as the building gets larger.

Smaller buildings cost more per square foot. The 750 sq ft backyard suite comes in at $585 per sq ft, against $425 for the largest fourplex, because foundations, a kitchen, a heat pump and a bathroom cost much the same whatever the floor area.

DesignUnitsBuilt sq ftHard costPer unitPer sq ft
Quadplex 0145,288$2,245,893$561,473$425
Quadplex 0245,236$2,293,518$573,380$438
Townhouse (4 units)45,175$2,307,250$576,813$446
Triplex 0133,096$1,496,279$498,760$483
Duplex 0122,056$950,172$475,086$462
Duplex 0223,084$1,236,966$618,483$401
Duplex 0322,620$1,162,284$581,142$444
ADU 01 (garden suite)11,050$555,576$555,576$529
ADU 021750$438,866$438,866$585
ADU 0311,715$731,493$731,493$427
Source: SHP Class D Estimate Report for the BC Ministry of Housing Standardized Designs, 21 August 2024. Hard construction cost only; excludes soft costs, utility connections, existing buildings, rock blasting or shoring, and electrical service upgrades.

Cost by region

The same report reviewed square-foot costs in seven regions. The last column applies each range to the 5,288 sq ft fourplex design, as a rough guide to what the same building would cost to build there.

For ZoneScout's cities: Burnaby, Richmond, Coquitlam and the North Shore sit closest to the Vancouver range; Surrey, Delta and the Langleys to Surrey's; Abbotsford and Chilliwack to Chilliwack's; the Okanagan cities to Kelowna's. The report does not price those cities separately, so treat these pairings as a starting point, not a quote.

RegionLow per sq ftHigh per sq ft5,288 sq ft fourplex at that rate
Vancouver$350$475$1.85M to $2.51M
Surrey$325$400$1.72M to $2.12M
Kelowna$325$425$1.72M to $2.25M
Nanaimo and Victoria$275$425$1.45M to $2.25M
Chilliwack$275$350$1.45M to $1.85M
Kamloops$275$350$1.45M to $1.85M
Prince George$275$350$1.45M to $1.85M
Low and high square-foot costs from the regional review in the Province's 2024 Class D estimate. The fourplex column is ZoneScout's arithmetic (rate x 5,288 sq ft), not a figure from the report.

What the hard cost leaves out

A builder's quote and a development budget include much more than the hard construction cost. The Province's 2023 modelling of small-scale multi-unit housing (published by the Province alongside its Bill 44 rules) adds soft costs of 26% of hard costs for townhouse-type buildings in the Lower Mainland and Fraser Valley, and 20% elsewhere, then a 10% contingency on hard and soft costs in the Lower Mainland and Fraser Valley.

Applied to the $2,245,893 Vancouver fourplex, that is about $2,830,000 with soft costs and about $3,113,000 with contingency, before development cost charges, utility connections, demolition, financing and land.

Costs on top of the hard cost

  1. Soft costs Design, engineering, surveys, permits, insurance and project management.
  2. Development cost charges Set by each city and regional district, often per unit.
  3. Service connections Water, sewer, storm and electrical connections, and any service upgrade the city requires.
  4. Demolition and site preparation Removing the existing house, and any blasting or shoring.
  5. Financing Interest and fees during construction.
  6. Land The lot itself, usually the largest single cost in Metro Vancouver.

Costs are still moving

These estimates are from August 2024. Statistics Canada's residential building construction price index (2023 = 100) stood at 108.9 for Vancouver and 120.2 for Victoria in the first quarter of 2026, up 1.4% and 6.0% from a year earlier. Victoria's index has climbed fastest, so the 2024 Victoria figures likely understate costs there today.

Get a number for your own lot

Every lot is different: how many units it allows, its setbacks and height, whether it has a lane, and what services are in the street all change the building and its cost. Check the address in ZoneScout first to see what the lot can hold, then ask a local builder to price it.

How many units can I build on my lot? · Bill 44 fourplex and sixplex requirements · Multiplex building envelope in BC · Bill 44 servicing exemption: water and sewer

Sources

  1. BC Ministry of Housing: SHP Class D Estimate Report, Standardized Designs (Aug 2024)
  2. Province of BC: SSMUH and TOA Scenarios in British Columbia (Dec 2023), construction cost model
  3. Statistics Canada: Building construction price indexes, first quarter 2026

Frequently asked questions

How much does it cost to build a fourplex in Vancouver?

The Province's 2024 estimate for its standard 3-storey fourplex designs is $2,245,893 to $2,293,518 in hard construction cost, about $425 to $438 per sq ft. Soft costs, contingency, development charges, connections, demolition and land come on top.

How much does a duplex cost to build in BC?

The Province's three standard duplex designs range from $950,172 to $1,236,966 in hard cost at Vancouver rates, or $401 to $462 per sq ft.

How much does a garden suite or backyard home cost?

The Province's three backyard suite (ADU) designs range from $438,866 for 750 sq ft to $731,493 for 1,715 sq ft in hard cost at Vancouver rates, or $427 to $585 per sq ft.

Is it cheaper to build outside Vancouver?

Per square foot, yes. The Province's regional review puts Vancouver at $350 to $475 per sq ft and Chilliwack, Kamloops and Prince George at $275 to $350. Development charges and land prices also differ by city.

Where do these numbers come from?

From the Class D cost estimate prepared in August 2024 for the BC Ministry of Housing's Standardized Designs Catalogue, the Province's 2023 small-scale multi-unit housing scenarios report, and Statistics Canada's building construction price index. A Class D estimate is preliminary; a builder's quote for your lot replaces it.

Related